New Spittal 275kV: grid connection queue
New Spittal 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Achies BESS | IGP ENERGY STORAGE 5 LIMITED | Battery storage | 200 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Mybster 2 GSP | SSEN Distribution | 3.9 km | ||
| Mybster 1 GSP | SSEN Distribution | 4.0 km | ||
| Halkirk Primary | SSEN Distribution | 11.0 km | 0 MW | 0 MW |
| Hastigrow Primary | SSEN Distribution | 12.5 km | 0 MW | 0 MW |
| Wick Primary | SSEN Distribution | 15.2 km | 0 MW | 5 MW |
| Latheron Primary | SSEN Distribution | 16.3 km | 0 MW | 1.1 MW |
Thinking of connecting near New Spittal 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Spittal 2 400kV: 1,000 MW waiting
- Spittal 400kV: 600 MW waiting
- Spittal 132kV: 462 MW waiting
- CAITHNESS ENERGY STORAGE 400KV SUBSTATION: 456 MW waiting
- Banniskirk 400kV: 3,258 MW waiting