Baillie 275KV: grid connection queue
Baillie 275KV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 48 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Sep 2030 to 30 Sep 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Baillie Greener Grid Park | Statkraft UK Ltd | Battery storage | 48 | 30 Sep 2030 | Medium | 30 Sep 2030 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Forss Primary | SSEN Distribution | 3.5 km | 0 MW | 0.3 MW |
| Dounreay GSP | SSEN Distribution | 4.6 km | ||
| Ormlie Primary | SSEN Distribution | 8.4 km | 0 MW | 9.9 MW |
| Thurso South GSP | SSEN Distribution | 9.6 km | ||
| Mount Pleasant Primary | SSEN Distribution | 10.4 km | 0 MW | 3.5 MW |
| Halkirk Primary | SSEN Distribution | 13.0 km | 0 MW | 0 MW |
Thinking of connecting near Baillie 275KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Limekilns 132/33kV substation: 232 MW waiting
- Pentland Floating Offshore Wind Farm 132/66kV substation: 100 MW waiting
- Thurso South 400kV: 500 MW waiting
- Thurso South 275kV: 400 MW waiting
- Thurso South: 36 MW waiting