Thurso South 400kV: grid connection queue

Thurso South 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Mybster 2 Battery StoragePOTENCIA ENERGY (MYBSTER) LTDBattery storage50031 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Mount Pleasant PrimarySSEN Distribution1.1 km0 MW3.5 MW
Ormlie PrimarySSEN Distribution1.5 km0 MW9.9 MW
Thurso South GSPSSEN Distribution2.4 km
Forss PrimarySSEN Distribution9.2 km0 MW0.3 MW
Halkirk PrimarySSEN Distribution10.3 km0 MW0 MW
Dounreay GSPSSEN Distribution13.8 km

Thinking of connecting near Thurso South 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points