Limekilns 132/33kV substation: grid connection queue
Limekilns 132/33kV substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 232 MW are waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 1 Dec 2030 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Limekiln | Limekiln Extension Limited | Onshore wind + storage | 61 | 1 Dec 2030 | High | 17 Oct 2032 | Scoping | 1 |
| Limekiln Extension 2 | BORALEX LIMITED | Onshore wind + storage | 171 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dounreay GSP | SSEN Distribution | 5.3 km | ||
| Forss Primary | SSEN Distribution | 8.7 km | 0 MW | 0.3 MW |
| Melvich Primary | SSEN Distribution | 10.5 km | 0 MW | 1.7 MW |
| Ormlie Primary | SSEN Distribution | 13.5 km | 0 MW | 9.9 MW |
| Thurso South GSP | SSEN Distribution | 14.3 km | ||
| Halkirk Primary | SSEN Distribution | 14.9 km | 0 MW | 0 MW |
Thinking of connecting near Limekilns 132/33kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Baillie 275KV: 48 MW waiting
- Melvich Community Wind Farm 132/33kV: 58 MW waiting
- Pentland Floating Offshore Wind Farm 132/66kV substation: 100 MW waiting
- Thurso South 400kV: 500 MW waiting
- Thurso South 275kV: 400 MW waiting