Trent Valley South Connection Node D 400kV: grid connection queue

Trent Valley South Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 6,420 MW are waiting to connect here (largest by capacity: gas and thermal, solar + storage). Contracted dates run from 30 Oct 2034 to 30 Oct 2035.

4projects in the queue
6,420 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Stoke BardolphStoke Bardolph 10 Renewables LimitedSolar + storage1,00030 Oct 2034Low30 Oct 2034Scoping1
Stoke BardolphSource Galileo LimitedBattery storage24030 Oct 2034Low30 Oct 2034Scoping1
Bute Hydrogen Project 1HALDANE ENERGY PROJECT 1 LIMITEDGas and thermal4,80030 Oct 2035Low30 Oct 2035Scoping1
Noventum - BudbyNOVENTUM POWER SOLAR 15 LIMITEDSolar + storage38030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Trent Valley South Connection Node D 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report