Trent Valley South Connection Node C 400kV: grid connection queue
Trent Valley South Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
10 projects with 4,589 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2034 to 30 Oct 2039.
10projects in the queue
4,589 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| NatPower Navenby Energy Park | NAVENBY ENERGY LIMITED | Battery storage | 1,000 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Grantham Solar Farm - RSL | SOUTH GRANTHAM ENERGY CENTRE LIMITED | Solar + storage | 810 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Bicker Fen | IB VOGT UK LTD | Solar + storage | 400 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Oak Holt Solar | RWE Renewables UK Solar and Storage Limited | Solar + storage | 400 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Cranwell Solar & BESS Farm | TRIO POWER LIMITED | Solar + storage | 300 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | none |
| Coddington | STARLIGHT ENERGY UK LIMITED | Battery storage | 240 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Barnby Solar Farm | KS SPV 75 LIMITED | Solar + storage | 250 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
| Grantham Generation | Aukera Energy Limited | Solar + storage | 700 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Noventum Navenby | NOVENTUM POWER SOLAR 4 LIMITED | Solar + storage | 249 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Kinder PV & BESS Station | IBV DANETHORPE LANE SOLAR LIMITED | Solar + storage | 240 | 30 Oct 2039 | Low | 30 Oct 2039 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Trent Valley South Connection Node C 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Trent Valley South Connection Node A 400kV: 2,500 MW waiting
- Ratcliffe-On-Soar 400kV: 590 MW waiting
- Ratcliffe-On-Soar 132kV: 190 MW waiting
- Derbyshire Connection Node F 132KV: 350 MW waiting
- Trent Valley South Connection Node B 400kV: 4,870 MW waiting