Trent Valley South Connection Node B 400kV: grid connection queue
Trent Valley South Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
9 projects with 4,870 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2033 to 30 Oct 2035.
9projects in the queue
4,870 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Natpower Thimbleby Green Energy Park | MOWBRAY ENERGY PARK LIMITED | Battery storage | 1,000 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| NatPower Allington Green Energy Park | COTTOM TO RYHALL ENERGY LIMITED | Battery storage | 1,000 | 30 Oct 2034 | Low | 30 Oct 2034 | Awaiting Consents | 1 |
| Project Number 6 | Trent BESS II Limited | Battery storage | 500 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Project Number 8 | Trent BESS I Limited | Battery storage | 500 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Worksop BESS | ARM Cedar Limited | Battery storage | 480 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Cottam-Ryhall Solar & BESS | CRH RENEWABLES LIMITED | Solar + storage | 400 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| TH Stow Manor | FRV Powertek Limited | Battery storage | 400 | 30 Oct 2034 | Low | 30 Oct 2034 | Awaiting Consents | none |
| Stack Hill Solar and Storage | RWE Renewables UK Solar and Storage Limited | Solar + storage | 350 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Apley Head Farm | Queequeg Renewables Ltd | Solar + storage | 240 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Trent Valley South Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Trent Valley South Connection Node D 400kV: 6,420 MW waiting
- Ratcliffe: 130 MW waiting
- Trent Valley South Connection Node G 400kV: 400 MW waiting
- Trent Valley South Connection Node A 400k: 400 MW waiting
- Stoke Bardolph 400kV: 400 MW waiting