Stoke Bardolph 400kV: grid connection queue
Stoke Bardolph 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stoke Bardolph 400 | ENSO GREEN HOLDINGS LIMITED | Solar + storage | 400 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Stoke Bardolph 400 | 31 Oct 2030 | 31 Oct 2031 | +12 months |
| 20 Oct 2026 | Stoke Bardolph 400 | 31 Oct 2032 | 31 Oct 2034 | +24 months |
Thinking of connecting near Stoke Bardolph 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Stoke Bardolph: 150 MW waiting
- Trent Valley South Connection Node D 400kV: 6,420 MW waiting
- Trent Valley South Connection Node B 400kV: 4,870 MW waiting
- Trent Valley South Connection Node C 400kV: 4,589 MW waiting
- Trent Valley South Connection Node G 400kV: 400 MW waiting