Stoke Bardolph: grid connection queue

Stoke Bardolph GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 30 Oct 2034 to 30 Oct 2034.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
RAF Newton PV solarBluestone Energy LtdSolar15030 Oct 2034Low30 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Stoke Bardolph?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points