Devonside 132/33kV: grid connection queue
Devonside 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 85 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2030 to 30 Apr 2039.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bankhead 25MW BESS | GPC 1169 Ltd | Battery storage | 25 | 30 Apr 2030 | Medium | 30 Apr 2030 | Scoping | none |
| Longriggs Energy Park | BROCKWELL STORAGE & SOLAR LIMITED | Battery storage | 60 | 30 Apr 2039 | Low | 30 Apr 2039 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dollar | SP Energy Networks | 3.5 km | 19 MW | 4.9 MW |
| Sauchie | SP Energy Networks | 4.5 km | 26 MW | 17 MW |
| Gartarry | SP Energy Networks | 4.6 km | 7.5 MW | 3.9 MW |
| Kelliebank | SP Energy Networks | 5.9 km | 11 MW | |
| Menstrie | SP Energy Networks | 7.1 km | 27 MW | 7.6 MW |
| Longannet | SP Energy Networks | 9.4 km | 11 MW | 7.1 MW |
Thinking of connecting near Devonside 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Devonside 132kV: 75 MW waiting
- Devilla Battery Storage 275kV substation: 500 MW waiting
- Kincardine North 400kV: 1,249 MW waiting
- Bainsford 132/33kV: 43 MW waiting
- Dunfermline 132/33kV: 60 MW waiting