Kincardine North 400kV: grid connection queue

Kincardine North 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 1,249 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2030 to 31 Oct 2031.

3projects in the queue
1,249 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
3date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
EcoKincardineEconergy International LimitedSolar + storage24931 Oct 2030Medium31 Oct 2030Scoping1
Hawkhill BESSGPC Project 12 LtdBattery storage50031 Oct 2031Medium31 Oct 2031Scoping1
Tulliallan BESSIGP ENERGY STORAGE 6 LIMITEDBattery storage50031 Oct 2031Medium31 Oct 2031Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
27 Oct 2026EcoKincardine31 Jul 202831 Oct 2030+27 months
20 Oct 2026Tulliallan BESS31 Jul 203131 Oct 2031+3 months
13 Oct 2026Tulliallan BESS31 Oct 203131 Jul 2031-3 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LongannetSP Energy Networks1.9 km11 MW7.1 MW
GartarrySP Energy Networks3.4 km7.5 MW3.9 MW
Earls RoadSP Energy Networks5.6 km8.1 MW
Zetland ParkSP Energy Networks6.4 km19 MW
WholeflatsSP Energy Networks7.2 km16 MW
KelliebankSP Energy Networks7.3 km11 MW

Thinking of connecting near Kincardine North 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points