Devonside 132kV: grid connection queue
Devonside 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 75 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Windburn Wind Farm | WINDBURN WIND FARM LIMITED | Onshore wind + storage | 75 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Windburn Wind Farm | 1 Oct 2034 | 31 Oct 2034 | +1 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dollar | SP Energy Networks | 3.5 km | 19 MW | 4.9 MW |
| Sauchie | SP Energy Networks | 4.5 km | 26 MW | 17 MW |
| Gartarry | SP Energy Networks | 4.6 km | 7.5 MW | 3.9 MW |
| Kelliebank | SP Energy Networks | 5.9 km | 11 MW | |
| Menstrie | SP Energy Networks | 7.1 km | 27 MW | 7.6 MW |
| Longannet | SP Energy Networks | 9.4 km | 11 MW | 7.1 MW |
Thinking of connecting near Devonside 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Devonside 132/33kV: 85 MW waiting
- Devilla Battery Storage 275kV substation: 500 MW waiting
- Kincardine North 400kV: 1,249 MW waiting
- Bainsford 132/33kV: 43 MW waiting
- Dunfermline 132/33kV: 60 MW waiting