Bainsford 132/33kV: grid connection queue
Bainsford 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 43 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 24 Nov 2025 to 24 Nov 2025.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bankside BESS | FALKIRK POWER LTD | Battery storage | 43 | 24 Nov 2025 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Earls Road | SP Energy Networks | 3.1 km | 8.1 MW | |
| Zetland Park | SP Energy Networks | 4.1 km | 19 MW | |
| Longannet | SP Energy Networks | 4.1 km | 11 MW | 7.1 MW |
| Callendar | SP Energy Networks | 4.8 km | 24 MW | 9.9 MW |
| Larbert | SP Energy Networks | 5.1 km | 25 MW | 1.4 MW |
| Wholeflats | SP Energy Networks | 5.6 km | 16 MW |
Thinking of connecting near Bainsford 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kincardine North 400kV: 1,249 MW waiting
- Denny North 275/132kV: 600 MW waiting
- Denny North: 350 MW waiting
- Devilla Battery Storage 275kV substation: 500 MW waiting
- Devonside 132/33kV: 85 MW waiting