Denny North: grid connection queue

Denny North · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 350 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2030 to 30 Oct 2030.

1project in the queue
350 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Denny BESSIGP ENERGY STORAGE 3 LIMITEDBattery storage35030 Oct 2030Medium30 Oct 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LarbertSP Energy Networks2.0 km25 MW1.4 MW
CamelonSP Energy Networks3.4 km10 MW
MyothillSP Energy Networks4.3 km9.7 MW
CallendarSP Energy Networks5.0 km24 MW9.9 MW
FalkirkSP Energy Networks5.2 km23 MW11 MW
Earls RoadSP Energy Networks7.3 km8.1 MW

Thinking of connecting near Denny North?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points