Bonnybridge 132/33kV: grid connection queue

Bonnybridge 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 90 MW are waiting to connect here (largest by capacity: battery storage, onshore wind). Contracted dates run from 1 Oct 2026 to 31 Oct 2030.

2projects in the queue
90 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Drummarnock Wind FarmDrummarnock Wind Farm LimitedOnshore wind301 Oct 2026n/aScopingnone
Scottish Water Bonnybridge STW 60MW BESSBluestone Energy LtdBattery storage6031 Oct 2030Medium31 Oct 2030Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Scottish Water Bonnybridge STW 60MW BESS31 Jul 203031 Oct 2030+3 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
MyothillSP Energy Networks3.2 km9.7 MW
Old InnsSP Energy Networks4.8 km11 MW
AbronhillSP Energy Networks6.0 km22 MW
KildrumSP Energy Networks6.9 km15 MW12 MW
KilsythSP Energy Networks7.0 km11 MW
GreenfauldsSP Energy Networks8.4 km13 MW

Thinking of connecting near Bonnybridge 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points