Devilla Battery Storage 275kV substation: grid connection queue
Devilla Battery Storage 275kV substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2027 to 30 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Alcemi Devilla Battery Energy Storage Facility | ALCEMI STORAGE DEVELOPMENTS 3 LIMITED | Battery storage | 500 | 30 Oct 2027 | High | 29 Oct 2029 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Longannet | SP Energy Networks | 2.4 km | 11 MW | 7.1 MW |
| Gartarry | SP Energy Networks | 3.2 km | 7.5 MW | 3.9 MW |
| Earls Road | SP Energy Networks | 7.3 km | 8.1 MW | |
| Zetland Park | SP Energy Networks | 7.8 km | 19 MW | |
| Boness Kinneil | SP Energy Networks | 8.0 km | 11 MW | 4.9 MW |
| Wholeflats | SP Energy Networks | 8.1 km | 16 MW |
Thinking of connecting near Devilla Battery Storage 275kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kincardine North 400kV: 1,249 MW waiting
- Bainsford 132/33kV: 43 MW waiting
- Devonside 132/33kV: 85 MW waiting
- Devonside 132kV: 75 MW waiting
- Dunfermline 132/33kV: 60 MW waiting