Dunfermline 132/33kV: grid connection queue
Dunfermline 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 60 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 12 Apr 2028 to 12 Apr 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Outh Muir Energy Park | Grupotec Solar UK 4 Ltd | Solar + storage | 60 | 12 Apr 2028 | High | 12 Apr 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Townhill | SP Energy Networks | 5.2 km | 22 MW | 8.9 MW |
| Nethertown | SP Energy Networks | 5.4 km | 27 MW | 14 MW |
| Pitreavie | SP Energy Networks | 6.9 km | 12 MW | |
| Calais A1 | SP Energy Networks | 7.6 km | 15 MW | |
| Calais A2 | SP Energy Networks | 7.6 km | 17 MW | |
| Halbeath | SP Energy Networks | 7.8 km | 34 MW | 26 MW |
Thinking of connecting near Dunfermline 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Halbeath 132kV: 150 MW waiting
- Devilla Battery Storage 275kV substation: 500 MW waiting
- Inverkeithing: 50 MW waiting
- Inverkeithing 132/33kV: 42 MW waiting
- Kincardine North 400kV: 1,249 MW waiting