Halbeath 132kV: grid connection queue

Halbeath 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Jul 2029 to 31 Jul 2029.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
HalbeathHALBEATH SOLAR LTDSolar + storage15031 Jul 2029Medium31 Jul 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
HalbeathSP Energy Networks1.1 km34 MW26 MW
Calais A1SP Energy Networks2.6 km15 MW
Calais A2SP Energy Networks2.6 km17 MW
CowdenbeathSP Energy Networks3.0 km16 MW
TownhillSP Energy Networks3.3 km22 MW8.9 MW
NethertownSP Energy Networks4.6 km27 MW14 MW

Thinking of connecting near Halbeath 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points