Mossmorran Storage BESS 132KV: grid connection queue
Mossmorran Storage BESS 132KV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Mossmorran Storage BESS | RUFUSIA LTD | Battery storage | 100 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cowdenbeath | SP Energy Networks | 1.9 km | 16 MW | |
| Kelty | SP Energy Networks | 4.4 km | 12 MW | 1.4 MW |
| Halbeath | SP Energy Networks | 5.0 km | 34 MW | 26 MW |
| Calais A1 | SP Energy Networks | 6.2 km | 15 MW | |
| Calais A2 | SP Energy Networks | 6.2 km | 17 MW | |
| Bowhill | SP Energy Networks | 6.7 km | 2.6 MW |
Thinking of connecting near Mossmorran Storage BESS 132KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Westfield 132/33kV: 1,199 MW waiting
- Westfield 400kV: 350 MW waiting
- WESTFIELD 400/275KV: 200 MW waiting
- Halbeath 132kV: 150 MW waiting
- LOCH GELLY COLLECTOR 132KV SUBSTATION: 200 MW waiting