Benzene

LOCH GELLY COLLECTOR 132KV SUBSTATION: grid connection queue

LOCH GELLY COLLECTOR 132KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Gresham House Mossmoran BESSMOSSMORRAN ENERGY STORAGE LIMITEDBattery storage20031 Oct 2031Medium31 Oct 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cluny RoadSP Energy Networks3.3 km6.6 MW
BowhillSP Energy Networks3.4 km2.6 MW
Linton LaneSP Energy Networks3.9 km8.3 MW4.4 MW
ChapelSP Energy Networks4.5 km12 MW3.4 MW
BurntislandSP Energy Networks5.9 km26 MW18 MW
RaithSP Energy Networks5.9 km22 MW16 MW

Thinking of connecting near LOCH GELLY COLLECTOR 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points