WESTFIELD 400/275KV: grid connection queue

WESTFIELD 400/275KV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2031 to 30 Oct 2031.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Fife Battery StorageCARLTON POWER LIMITEDBattery storage20030 Oct 2031Medium30 Oct 2031Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
KeltySP Energy Networks3.3 km12 MW1.4 MW
BowhillSP Energy Networks3.3 km2.6 MW
CowdenbeathSP Energy Networks4.1 km16 MW
Cluny RoadSP Energy Networks6.6 km6.6 MW
Linton LaneSP Energy Networks7.6 km8.3 MW4.4 MW
ChapelSP Energy Networks7.8 km12 MW3.4 MW

Thinking of connecting near WESTFIELD 400/275KV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points