Lister Drive 275kV: grid connection queue
Lister Drive 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 114 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Sep 2026 to 30 Sep 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lister Drive Shaw | Carnegie (BES) Ltd | Battery storage | 57 | 1 Sep 2026 | n/a | Scoping | none | |
| Lister Battery (formerly Lister Drive) | LISTER BATTERY LTD | Battery storage | 57 | 30 Sep 2029 | Medium | 30 Sep 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 21 Jul 2026 | Lister Battery (formerly Lister Drive) | 31 Oct 2023 | 30 Sep 2029 | +71 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Mossley Hill T1 | SP Energy Networks | 0.4 km | 7.2 MW | 17 MW |
| Mather Ave T1 | SP Energy Networks | 0.8 km | 7.2 MW | 17 MW |
| Allerton T1 | SP Energy Networks | 1.0 km | 5.7 MW | 24 MW |
| Aigburth Vale T1 | SP Energy Networks | 1.3 km | 7.2 MW | 17 MW |
| Yew Tree Rd T1 | SP Energy Networks | 1.4 km | 5.7 MW | 24 MW |
| Wavertree T1 | SP Energy Networks | 1.5 km | 7.2 MW | 17 MW |
Thinking of connecting near Lister Drive 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: 1,260 MW waiting
- Rainhill: 86 MW waiting
- Kirkby 275kV: 400 MW waiting
- Kirkby 275/33kV: 114 MW waiting
- Fiddlers Ferry 275kV: 1,300 MW waiting