Fiddlers Ferry 275kV: grid connection queue
Fiddlers Ferry 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,300 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 12 Feb 2027 to 31 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| SSE Fiddlers Ferry Battery Energy Storage | LITTLETON PASTURES SOLAR LIMITED | Battery storage | 150 | 12 Feb 2027 | High | 11 Feb 2029 | Consents Approved | 2 |
| Penketh Hall Farm | Net Zero One Ltd | Battery storage | 250 | 1 Sep 2027 | High | 31 Aug 2029 | Scoping | 1 |
| Fiddlers Ferry BESS | FIDDLERS FERRY LTD | Battery storage | 900 | 31 Oct 2027 | High | 30 Oct 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 11 Aug 2026 | SSE Fiddlers Ferry Battery Energy Storage | 30 Oct 2026 | 12 Feb 2027 | +3 months |
| 30 Jun 2026 | SSE Fiddlers Ferry Battery Energy Storage | 12 Feb 2027 | 30 Oct 2026 | -3 months |
| 9 Jun 2026 | SSE Fiddlers Ferry Battery Energy Storage | 30 Oct 2026 | 12 Feb 2027 | +3 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Usac T1 | SP Energy Networks | 1.7 km | 4 MW | 22 MW |
| Pilk Sullivan T2 | SP Energy Networks | 2.0 km | 4 MW | 22 MW |
| Pilk Sullivan T1 | SP Energy Networks | 2.0 km | 4 MW | 22 MW |
| Widnes Rd T1 | SP Energy Networks | 2.1 km | 4.2 MW | 4.8 MW |
| Hornsbridge T1 | SP Energy Networks | 2.4 km | 4.5 MW | 4.1 MW |
| Lugsdale T1 | SP Energy Networks | 2.5 km | 4 MW | 22 MW |
Thinking of connecting near Fiddlers Ferry 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cheshire Connection Node B 400kV: 800 MW waiting
- Rainhill: 86 MW waiting
- Frodsham 400kV: 740 MW waiting
- Frodsham 132kV: 350 MW waiting
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: 1,260 MW waiting