Frodsham 400kV: grid connection queue

Frodsham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 740 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 27 Oct 2028 to 1 Nov 2037.

2projects in the queue
740 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
240 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Weaver BESSFrodsham Devco LimitedBattery storage24027 Oct 2028High27 Oct 2030Scoping1
Clean Planet SolarClean Planet Solar Farm LimitedSolar + storage5001 Nov 2037Low1 Nov 2037Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
3 Nov 2026Weaver BESS11 Nov 203727 Oct 2028-108 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dutton Gt2SP Energy Networks2.2 km64 MW33 MW
Frodsham Local T1SP Energy Networks2.6 km1.9 MW
Bass Charrington T1SP Energy Networks2.8 km3.6 MW15 MW
Bass Charrington T2SP Energy Networks2.8 km3.6 MW15 MW
Clifton T1SP Energy Networks3.2 km3.6 MW15 MW
Murdishaw T1SP Energy Networks3.4 km0.3 MW6.9 MW

Thinking of connecting near Frodsham 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points