Cheshire Connection Node B 400kV: grid connection queue

Cheshire Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 800 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.

2projects in the queue
800 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
NatPower Connah Quay Green Energy ParkCONNAHS QUAY ENERGY LIMITEDBattery storage50030 Oct 2037Low30 Oct 2037Scoping1
Lightsource BodelwyddanLightsource Renewable UK Development LimitedBattery storage30030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Daresbury Pk T1SP Energy Networks0.8 km1.5 MW3.9 MW
Daresbury Npl T1SP Energy Networks1.5 km1.5 MW3.9 MW
Murdishaw T1SP Energy Networks1.8 km0.3 MW6.9 MW
Bass Charrington T1SP Energy Networks2.2 km3.6 MW15 MW
Bass Charrington T2SP Energy Networks2.2 km3.6 MW15 MW
Moore Gt1SP Energy Networks2.4 km64 MW33 MW

Thinking of connecting near Cheshire Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points