Cheshire Connection Node B 400kV: grid connection queue
Cheshire Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 800 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| NatPower Connah Quay Green Energy Park | CONNAHS QUAY ENERGY LIMITED | Battery storage | 500 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Lightsource Bodelwyddan | Lightsource Renewable UK Development Limited | Battery storage | 300 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Daresbury Pk T1 | SP Energy Networks | 0.8 km | 1.5 MW | 3.9 MW |
| Daresbury Npl T1 | SP Energy Networks | 1.5 km | 1.5 MW | 3.9 MW |
| Murdishaw T1 | SP Energy Networks | 1.8 km | 0.3 MW | 6.9 MW |
| Bass Charrington T1 | SP Energy Networks | 2.2 km | 3.6 MW | 15 MW |
| Bass Charrington T2 | SP Energy Networks | 2.2 km | 3.6 MW | 15 MW |
| Moore Gt1 | SP Energy Networks | 2.4 km | 64 MW | 33 MW |
Thinking of connecting near Cheshire Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Frodsham 400kV: 740 MW waiting
- Frodsham 132kV: 350 MW waiting
- Fiddlers Ferry 275kV: 1,300 MW waiting
- Cheshire Connection Node A 400kV: 5,130 MW waiting
- Rainhill: 86 MW waiting