Rainhill: grid connection queue
Rainhill GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 86 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 25 Sep 2026 to 25 Sep 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sizing John (Rainhill) | SIZING JOHN LIMITED | Battery storage | 86 | 25 Sep 2026 | n/a | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Whiston Hosp T1 | SP Energy Networks | 0.3 km | 5.6 MW | 14 MW |
| Rainhill Local T1 | SP Energy Networks | 1.5 km | 5.6 MW | 14 MW |
| Prescot Gt1A | SP Energy Networks | 1.7 km | 120 MW | 31 MW |
| Prescot Gt1B | SP Energy Networks | 1.7 km | 86 MW | 24 MW |
| Prescot Gt1A | SP Energy Networks | 1.7 km | 120 MW | 31 MW |
| Prescot Gt1B | SP Energy Networks | 1.7 km | 86 MW | 24 MW |
Thinking of connecting near Rainhill?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: 1,260 MW waiting
- Fiddlers Ferry 275kV: 1,300 MW waiting
- Kirkby 275kV: 400 MW waiting
- Kirkby 275/33kV: 114 MW waiting
- Lister Drive 275kV: 114 MW waiting