MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: grid connection queue
MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,260 MW are waiting to connect here (largest by capacity: gas and thermal, battery storage). Contracted dates run from 30 Oct 2037 to 1 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Shotwick BESS | Shotwick Land Limited | Battery storage | 350 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Protos Power Station | Keadby Generation Limited | Gas and thermal | 910 | 1 Nov 2037 | Low | 1 Nov 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Knowsley T1 | SP Energy Networks | 1.3 km | 2.1 MW | 5.5 MW |
| Marled Hey T1 | SP Energy Networks | 1.4 km | 2.1 MW | 5.5 MW |
| Ainsworth Lane T1 | SP Energy Networks | 1.5 km | 13 MW | 11 MW |
| Palco T1 | SP Energy Networks | 1.6 km | 13 MW | 11 MW |
| Kelco T1 | SP Energy Networks | 1.9 km | 3.2 MW | 8.2 MW |
| Croxteth T1 | SP Energy Networks | 1.9 km | 4.9 MW | 14 MW |
Thinking of connecting near MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kirkby 275kV: 400 MW waiting
- Kirkby 275/33kV: 114 MW waiting
- Rainhill: 86 MW waiting
- Lister Drive 275kV: 114 MW waiting
- Fiddlers Ferry 275kV: 1,300 MW waiting