Kirkby 275kV: grid connection queue
Kirkby 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2028 to 30 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kirkby Green Energy Centre | KIRKBY GREEN NG LIMITED | Solar + storage | 400 | 30 Oct 2028 | High | 30 Oct 2030 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 28 Jul 2026 | Kirkby | 30 Sep 2025 | 31 Oct 2027 | +25 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kirkby Central T1 | SP Energy Networks | 0.4 km | 6.6 MW | 9.7 MW |
| Westvale T1 | SP Energy Networks | 0.5 km | 6.6 MW | 9.7 MW |
| Northwood T1 | SP Energy Networks | 1.2 km | 6.6 MW | 9.7 MW |
| Southdene T1 | SP Energy Networks | 1.4 km | 13 MW | 11 MW |
| Dickinsons T1 | SP Energy Networks | 1.9 km | 6 MW | 14 MW |
| Otis Elevator T1 | SP Energy Networks | 2.0 km | 2.4 MW | 4.6 MW |
Thinking of connecting near Kirkby 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kirkby 275/33kV: 114 MW waiting
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: 1,260 MW waiting
- Rainhill: 86 MW waiting
- Lister Drive 275kV: 114 MW waiting
- Fiddlers Ferry 275kV: 1,300 MW waiting