Kirkby 275/33kV: grid connection queue
Kirkby 275/33kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 114 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Aug 2027 to 31 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kirkby (Tertiary) | PIVOTED POWER LLP | Solar + storage | 57 | 30 Aug 2027 | High | 29 Aug 2029 | Scoping | 1 |
| Kirkby | KIRKBY BATTERY STORAGE LTD | Battery storage | 57 | 31 Oct 2027 | High | 30 Oct 2029 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kirkby Central T1 | SP Energy Networks | 0.4 km | 6.6 MW | 9.7 MW |
| Westvale T1 | SP Energy Networks | 0.5 km | 6.6 MW | 9.7 MW |
| Northwood T1 | SP Energy Networks | 1.2 km | 6.6 MW | 9.7 MW |
| Southdene T1 | SP Energy Networks | 1.4 km | 13 MW | 11 MW |
| Dickinsons T1 | SP Energy Networks | 1.9 km | 6 MW | 14 MW |
| Otis Elevator T1 | SP Energy Networks | 2.0 km | 2.4 MW | 4.6 MW |
Thinking of connecting near Kirkby 275/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kirkby 275kV: 400 MW waiting
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: 1,260 MW waiting
- Rainhill: 86 MW waiting
- Lister Drive 275kV: 114 MW waiting
- Fiddlers Ferry 275kV: 1,300 MW waiting