MID WALES CONNECTION NODE A 400KV SUBSTATION: grid connection queue

MID WALES CONNECTION NODE A 400KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 799 MW are waiting to connect here (largest by capacity: mixed and other, onshore wind + storage). Contracted dates run from 30 Oct 2037 to 31 Oct 2037.

4projects in the queue
799 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Mynydd Y GwyntEDF ENERGY RENEWABLES LIMITEDOnshore wind + storage10030 Oct 2037Low30 Oct 2037Scopingnone
Galileo 09GALILEO 09 LIMITEDMixed and other29731 Oct 2037Low31 Oct 2037Scoping1
Lightsource BerthlwydLightsource Renewable UK Development LimitedMixed and other24031 Oct 2037Low31 Oct 2037Scoping1
Garn Fach Wind FarmEDF ENERGY RENEWABLES LIMITEDOnshore wind + storage16231 Oct 2037Low31 Oct 2037Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Llanidloes T1SP Energy Networks3.2 km-3.5 MW1.5 MW
Llanidloes T2SP Energy Networks3.2 km-3.5 MW1.5 MW
Caersws T1SP Energy Networks13.9 km8.1 MW3.8 MW
Mochdre T1SP Energy Networks16.9 km8.3 MW4.1 MW
Milford T1SP Energy Networks16.9 km3.2 MW
Newtown Gt2SP Energy Networks19.9 km16 MW61 MW

Thinking of connecting near MID WALES CONNECTION NODE A 400KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.