Legacy 400kV: grid connection queue

Legacy 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 1,714 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 31 Aug 2024 to 30 Oct 2037.

4projects in the queue
1,714 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
1,257 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Legacy Tertiary ConnectionHD639LEG LIMITEDBattery storage5731 Aug 2024n/aConsents Approvednone
Legacy Green Energy CentreLEGACY GREEN ENERGY LIMITEDBattery storage1,20030 Oct 2027High29 Oct 2029Awaiting Consents1
Plas Power Estate North TertiaryLIGHTSOURCE SPV 192 LIMITEDSolar + storage5731 May 2028High31 May 2030Scopingnone
Legacy 400ENSO GREEN HOLDINGS LIMITEDMixed and other40030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Llanddu Quarry T1SP Energy Networks4.2 km2.8 MW0.6 MW
Llanfyllin T1SP Energy Networks6.2 km1.4 MW2.1 MW
Llanfyllin T2SP Energy Networks6.2 km1.4 MW2.1 MW
Llandrinio T1SP Energy Networks7.0 km4.7 MW2.1 MW
Llynclys T1SP Energy Networks7.2 km8.5 MW3.3 MW
Llansilin T1SP Energy Networks8.2 km7.7 MW3.5 MW

Thinking of connecting near Legacy 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.