Shrewsbury 400/33kV: grid connection queue
Shrewsbury 400/33kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Sep 2028 to 30 Sep 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| JBM Solar 12 - Shrewsbury Solar | RWE Renewables UK Solar and Storage Limited | Solar + storage | 50 | 30 Sep 2028 | High | 30 Sep 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Shawbury T1 | SP Energy Networks | 11.4 km | 1.7 MW | |
| Baschurch T1 | SP Energy Networks | 12.9 km | 0.1 MW | 1 MW |
| Express Foods T1 | SP Energy Networks | 14.2 km | 6 MW | |
| Wem T1 | SP Energy Networks | 17.3 km | 3 MW | |
| Wem East T1 | SP Energy Networks | 17.3 km | 4.3 MW |
Thinking of connecting near Shrewsbury 400/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Shrewsbury 400kV: 431 MW waiting
- Ironbridge 400kV: 1,300 MW waiting
- Legacy 400kV: 1,714 MW waiting
- Chirk: 843 MW waiting
- Chirk 132kV: 100 MW waiting