Chirk: grid connection queue

Chirk GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

6 projects with 843 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 4 Feb 2027 to 1 Nov 2033.

6projects in the queue
843 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
693 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Moel y LlynWaun Hesgog Energy Park LimitedOnshore wind2514 Feb 2027High3 Apr 2029Scopingnone
DolyfardynLlyn Lort Energy Park LimitedOnshore wind1654 Feb 2027High3 Apr 2029Scopingnone
LlwynygogESGAIR GALED ENERGY PARK LIMITEDOnshore wind1254 Feb 2027High3 Apr 2029Scopingnone
Bryn TiltiRHIWLAS ENERGY PARK LIMITEDOnshore wind1064 Feb 2027High3 Apr 2029Scopingnone
Blaen y GlynBANC DU ENERGY PARK LIMITEDOnshore wind464 Feb 2027High3 Apr 2029Scopingnone
Maesnant Energy ParkMaesnant Energy Park LimitedOnshore wind1501 Nov 2033Low1 Nov 2033Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
29 Sep 2026Bryn Tilti19 Jul 20284 Feb 2027-17 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cadburys Kronospan T2SP Energy Networks2.0 km2.4 MW4.4 MW
Cadburys Kronospan T1SP Energy Networks2.0 km2.4 MW4.4 MW
Monsanto T1SP Energy Networks2.5 km6 MW
Ruabon T1SP Energy Networks3.6 km-1.2 MW2 MW
Ifton T1SP Energy Networks4.5 km19 MW3 MW
Ifton T2SP Energy Networks4.5 km19 MW3 MW

Thinking of connecting near Chirk?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points