Chirk: grid connection queue
Chirk GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
6 projects with 843 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 4 Feb 2027 to 1 Nov 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Moel y Llyn | Waun Hesgog Energy Park Limited | Onshore wind | 251 | 4 Feb 2027 | High | 3 Apr 2029 | Scoping | none |
| Dolyfardyn | Llyn Lort Energy Park Limited | Onshore wind | 165 | 4 Feb 2027 | High | 3 Apr 2029 | Scoping | none |
| Llwynygog | ESGAIR GALED ENERGY PARK LIMITED | Onshore wind | 125 | 4 Feb 2027 | High | 3 Apr 2029 | Scoping | none |
| Bryn Tilti | RHIWLAS ENERGY PARK LIMITED | Onshore wind | 106 | 4 Feb 2027 | High | 3 Apr 2029 | Scoping | none |
| Blaen y Glyn | BANC DU ENERGY PARK LIMITED | Onshore wind | 46 | 4 Feb 2027 | High | 3 Apr 2029 | Scoping | none |
| Maesnant Energy Park | Maesnant Energy Park Limited | Onshore wind | 150 | 1 Nov 2033 | Low | 1 Nov 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 29 Sep 2026 | Bryn Tilti | 19 Jul 2028 | 4 Feb 2027 | -17 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cadburys Kronospan T2 | SP Energy Networks | 2.0 km | 2.4 MW | 4.4 MW |
| Cadburys Kronospan T1 | SP Energy Networks | 2.0 km | 2.4 MW | 4.4 MW |
| Monsanto T1 | SP Energy Networks | 2.5 km | 6 MW | |
| Ruabon T1 | SP Energy Networks | 3.6 km | -1.2 MW | 2 MW |
| Ifton T1 | SP Energy Networks | 4.5 km | 19 MW | 3 MW |
| Ifton T2 | SP Energy Networks | 4.5 km | 19 MW | 3 MW |
Thinking of connecting near Chirk?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Chirk 132kV: 100 MW waiting
- Legacy 400kV: 1,714 MW waiting
- Gwyddelwern 400kV: 233 MW waiting
- Sealand 400kV: 500 MW waiting
- Connah's Quay 400kV: 1,210 MW waiting