Connah's Quay 400kV: grid connection queue

Connah's Quay 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,210 MW are waiting to connect here (largest by capacity: offshore wind, hydro, pumped storage and tidal). Contracted dates run from 1 Dec 2030 to 1 Nov 2033.

2projects in the queue
1,210 MWwaiting to connect
1,381 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Port of MostynMOSTYN SEAPOWER LIMITEDHydro, pumped storage and tidal2101 Dec 2030Medium1 Dec 2030Scoping1
Icewind Connah's QuayKARI ENERGY LIMITEDOffshore wind1,0001 Nov 2033Low1 Nov 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Llandyrnog T1SP Energy Networks2.8 km2.4 MW
Cefn Mawr T1SP Energy Networks6.5 km2.3 MW
Ruthin T1SP Energy Networks7.2 km-1.2 MW5.6 MW
Wimpeys Pant Quarry T1SP Energy Networks7.2 km2 MW1.1 MW
Wimpeys Pant Quarry T2SP Energy Networks7.2 km2 MW1.1 MW
Holywell Gt1SP Energy Networks8.0 km89 MW22 MW

Thinking of connecting near Connah's Quay 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.