Connah's Quay 400kV: grid connection queue
Connah's Quay 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,210 MW are waiting to connect here (largest by capacity: offshore wind, hydro, pumped storage and tidal). Contracted dates run from 1 Dec 2030 to 1 Nov 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Port of Mostyn | MOSTYN SEAPOWER LIMITED | Hydro, pumped storage and tidal | 210 | 1 Dec 2030 | Medium | 1 Dec 2030 | Scoping | 1 |
| Icewind Connah's Quay | KARI ENERGY LIMITED | Offshore wind | 1,000 | 1 Nov 2033 | Low | 1 Nov 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Llandyrnog T1 | SP Energy Networks | 2.8 km | 2.4 MW | |
| Cefn Mawr T1 | SP Energy Networks | 6.5 km | 2.3 MW | |
| Ruthin T1 | SP Energy Networks | 7.2 km | -1.2 MW | 5.6 MW |
| Wimpeys Pant Quarry T1 | SP Energy Networks | 7.2 km | 2 MW | 1.1 MW |
| Wimpeys Pant Quarry T2 | SP Energy Networks | 7.2 km | 2 MW | 1.1 MW |
| Holywell Gt1 | SP Energy Networks | 8.0 km | 89 MW | 22 MW |
Thinking of connecting near Connah's Quay 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Wales connection Node A 400kV: 1,273 MW waiting
- Bodelwyddan 400kV: 3,468 MW waiting
- Sealand 400kV: 500 MW waiting
- Gwyddelwern 400kV: 233 MW waiting
- Capenhurst: 440 MW waiting