Capenhurst: grid connection queue
Capenhurst GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 440 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Hill Farm | QAIR RENEWABLES UK LIMITED | Battery storage | 240 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Mill Hey_Capenhurst BESS | FIRSTWAY SOLAR LTD | Battery storage | 200 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Hill Farm | 30 Oct 2035 | 30 Oct 2037 | +24 months |
| 13 Oct 2026 | Hill Farm | 31 Oct 2037 | 30 Oct 2035 | -24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Mannings La T1 | SP Energy Networks | 0.9 km | 1.4 MW | 12 MW |
| Upton Heath T1 | SP Energy Networks | 0.9 km | 1.4 MW | 12 MW |
| Pipers Ash T1 | SP Energy Networks | 1.6 km | 4.7 MW | 7.1 MW |
| Guilden Sutton Gt1 | SP Energy Networks | 1.7 km | 95 MW | 32 MW |
| Guilden Sutton Gt1 | SP Energy Networks | 1.7 km | 95 MW | 32 MW |
| Wervin T1 | SP Energy Networks | 1.7 km | 4.3 MW |
Thinking of connecting near Capenhurst?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Capenhurst 275kV: 400 MW waiting
- Capenhurst 400kV: 57 MW waiting
- Sealand 400kV: 500 MW waiting
- Frodsham 400kV: 740 MW waiting
- Frodsham 132kV: 350 MW waiting