Capenhurst 275kV: grid connection queue
Capenhurst 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 14 Sep 2033 to 14 Sep 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Capenhurst | ENSO GREEN HOLDINGS Q LIMITED | Solar + storage | 400 | 14 Sep 2033 | Low | 14 Sep 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Mannings La T1 | SP Energy Networks | 0.9 km | 1.4 MW | 12 MW |
| Upton Heath T1 | SP Energy Networks | 0.9 km | 1.4 MW | 12 MW |
| Pipers Ash T1 | SP Energy Networks | 1.6 km | 4.7 MW | 7.1 MW |
| Guilden Sutton Gt1 | SP Energy Networks | 1.7 km | 95 MW | 32 MW |
| Guilden Sutton Gt1 | SP Energy Networks | 1.7 km | 95 MW | 32 MW |
| Wervin T1 | SP Energy Networks | 1.7 km | 4.3 MW |
Thinking of connecting near Capenhurst 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Capenhurst: 440 MW waiting
- Capenhurst 400kV: 57 MW waiting
- Sealand 400kV: 500 MW waiting
- Frodsham 400kV: 740 MW waiting
- Frodsham 132kV: 350 MW waiting