Gwyddelwern 400kV: grid connection queue
Gwyddelwern 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 233 MW are waiting to connect here (largest by capacity: onshore wind, mixed and other). Contracted dates run from 1 Jun 2027 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Gaerwen Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind | 67 | 1 Jun 2027 | High | 29 Jul 2029 | Awaiting Consents | none |
| Mwdwl Eithin Energy Park | MOEL CHWA ENERGY PARK LIMITED | Onshore wind | 81 | 30 Jun 2030 | High | 16 May 2032 | Scoping | none |
| Derwydd Bach Energy Park | CONSTANTINE WIND ENERGY LIMITED | Mixed and other | 85 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Glan-Yr-Afon T1 | SP Energy Networks | 2.5 km | 0.6 MW | 5 MW |
| Corwen T1 | SP Energy Networks | 4.0 km | 6.6 MW | 2.2 MW |
| Bala T1 | SP Energy Networks | 12.1 km | 10 MW | 4 MW |
| Tryweryn T1 | SP Energy Networks | 15.1 km | 5.4 MW | 2.1 MW |
| Llanfwrog T1 | SP Energy Networks | 15.2 km | -1.2 MW | 5.6 MW |
| Ruthin T1 | SP Energy Networks | 17.6 km | -1.2 MW | 5.6 MW |
Thinking of connecting near Gwyddelwern 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Wales connection Node A 400kV: 1,273 MW waiting
- Connah's Quay 400kV: 1,210 MW waiting
- Chirk: 843 MW waiting
- Chirk 132kV: 100 MW waiting
- Bodelwyddan 400kV: 3,468 MW waiting