Chirk 132kV: grid connection queue
Chirk 132kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Nov 2037 to 1 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Llyn Lort II Energy Park | Llyn Lort II Energy Park Limited | Onshore wind | 100 | 1 Nov 2037 | Low | 1 Nov 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cadburys Kronospan T2 | SP Energy Networks | 2.0 km | 2.4 MW | 4.4 MW |
| Cadburys Kronospan T1 | SP Energy Networks | 2.0 km | 2.4 MW | 4.4 MW |
| Monsanto T1 | SP Energy Networks | 2.5 km | 6 MW | |
| Ruabon T1 | SP Energy Networks | 3.6 km | -1.2 MW | 2 MW |
| Ifton T1 | SP Energy Networks | 4.5 km | 19 MW | 3 MW |
| Ifton T2 | SP Energy Networks | 4.5 km | 19 MW | 3 MW |
Thinking of connecting near Chirk 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.