Benzene

Chirk 132kV: grid connection queue

Chirk 132kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Nov 2037 to 1 Nov 2037.

1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Llyn Lort II Energy ParkLlyn Lort II Energy Park LimitedOnshore wind1001 Nov 2037Low1 Nov 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cadburys Kronospan T2SP Energy Networks2.0 km2.4 MW4.4 MW
Cadburys Kronospan T1SP Energy Networks2.0 km2.4 MW4.4 MW
Monsanto T1SP Energy Networks2.5 km6 MW
Ruabon T1SP Energy Networks3.6 km-1.2 MW2 MW
Ifton T1SP Energy Networks4.5 km19 MW3 MW
Ifton T2SP Energy Networks4.5 km19 MW3 MW

Thinking of connecting near Chirk 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points