Ironbridge 400kV: grid connection queue
Ironbridge 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,300 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ironbridge Green Energy Centre | IRONBRIDGE GREEN NG LIMITED | Solar + storage | 400 | 30 Oct 2029 | Medium | 30 Oct 2029 | Awaiting Consents | 1 |
| Ironbridge | IGP SOLAR 16 LIMITED | Solar + storage | 600 | 30 Apr 2031 | Medium | 30 Apr 2031 | Scoping | none |
| ELMYA REDNAL | ELMYA RPC UK REDNAL LIMITED | Battery storage | 300 | 30 Oct 2034 | Low | 30 Oct 2034 | Awaiting Consents | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Ironbridge Green Energy Centre | 30 Oct 2032 | 30 Oct 2029 | -36 months |
| 13 Oct 2026 | Ironbridge Green Energy Centre | 30 Oct 2029 | 30 Oct 2032 | +36 months |
Thinking of connecting near Ironbridge 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.