Ironbridge 400kV: grid connection queue

Ironbridge 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,300 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2034.

3projects in the queue
1,300 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Ironbridge Green Energy CentreIRONBRIDGE GREEN NG LIMITEDSolar + storage40030 Oct 2029Medium30 Oct 2029Awaiting Consents1
IronbridgeIGP SOLAR 16 LIMITEDSolar + storage60030 Apr 2031Medium30 Apr 2031Scopingnone
ELMYA REDNALELMYA RPC UK REDNAL LIMITEDBattery storage30030 Oct 2034Low30 Oct 2034Awaiting Consents1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Ironbridge Green Energy Centre30 Oct 203230 Oct 2029-36 months
13 Oct 2026Ironbridge Green Energy Centre30 Oct 202930 Oct 2032+36 months

Thinking of connecting near Ironbridge 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.