Penn 275kV: grid connection queue
Penn 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jun 2033 to 30 Jun 2033.
1project in the queue
249 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Penn Battery Storage | ANGLO ENERGY STORAGE LTD | Battery storage | 249 | 30 Jun 2033 | Low | 30 Jun 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Penn 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Penn 132kV: 100 MW waiting
- Oldbury 275kV: 57 MW waiting
- Ocker Hill 275kV: 240 MW waiting
- Ocker Hill C 132kV: 99 MW waiting
- Bushbury 275kV: 480 MW waiting