Ocker Hill 275kV: grid connection queue
Ocker Hill 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 240 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ocker Hill - Gresham House | Ocker Hill Storage Limited | Battery storage | 240 | 30 Oct 2029 | Medium | 30 Oct 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | Ocker Hill - Gresham House | 30 Oct 2027 | 30 Oct 2029 | +24 months |
Thinking of connecting near Ocker Hill 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Ocker Hill C 132kV: 99 MW waiting
- Oldbury 275kV: 57 MW waiting
- Penn 275kV: 249 MW waiting
- Penn 132kV: 100 MW waiting
- Hams Hall 400kV: 1,075 MW waiting