Hams Hall 400kV: grid connection queue
Hams Hall 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,075 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2028 to 31 Oct 2032.
2projects in the queue
1,075 MWwaiting to connect
350 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
1,025 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Hams Hall Green Energy Centre | HAMS HALL NG LIMITED | Solar + storage | 1,025 | 30 Oct 2028 | High | 30 Oct 2030 | Scoping | 1 |
| WELBAR ENERGY STORAGE | WELBAR ENERGY STORAGE LIMITED | Battery storage | 50 | 31 Oct 2032 | Low | 31 Oct 2032 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Hams Hall 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Harlaston 400kV: 600 MW waiting
- Warwickshire Connection Node B 132kV: 100 MW waiting
- Ocker Hill 275kV: 240 MW waiting
- Ocker Hill C 132kV: 99 MW waiting
- Oldbury 275kV: 57 MW waiting