Mid Wales West 132kV: grid connection queue

Mid Wales West 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out). Planning record: whether we found the project in the government's Renewable Energy Planning Database (Q3 2026). "None found" means no planning record of that technology and a similar size within 20 km of the connection point; the database can lag, so check with the council.

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGatePlanning record
Carnedd Wen Wind FarmCARNEDD WEN WIND FARM LIMITEDOnshore wind15031 Oct 2030High8 Sep 2032ScopingNot stated

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cemmaes Rd T1SP Energy Networks12.3 km3.5 MW1.5 MW
Llanfair Caereinion T1SP Energy Networks18.1 km4 MW2 MW
Machynlleth T1SP Energy Networks19.2 km4.6 MW1.1 MW
Machynlleth T2SP Energy Networks19.2 km-1.7 MW2.3 MW
Caersws T1SP Energy Networks19.4 km8.1 MW3.8 MW

Thinking of connecting near Mid Wales West 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points