Trawsfynydd 275kV: grid connection queue
Trawsfynydd 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 940 MW is waiting to connect here (largest by capacity: nuclear). Contracted dates run from 1 Nov 2037 to 1 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Trawsfynydd B Cwmni Egino | Cwmni Egino | Nuclear | 940 | 1 Nov 2037 | Low | 1 Nov 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Maentwrog Gt1 | SP Energy Networks | 9.7 km | -29.8 MW | 4.3 MW |
| Maentwrog Gt2 | SP Energy Networks | 9.7 km | -29.8 MW | 4.3 MW |
| Maentwrog T1 | SP Energy Networks | 9.7 km | 9.4 MW | 5.9 MW |
| Maentwrog Gt1 | SP Energy Networks | 9.7 km | -29.8 MW | 4.3 MW |
| Maentwrog T1 | SP Energy Networks | 9.7 km | 9.4 MW | 5.9 MW |
| Maentwrog Gt2 | SP Energy Networks | 9.7 km | -29.8 MW | 4.3 MW |
Thinking of connecting near Trawsfynydd 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pentir 400kV: 1,082 MW waiting
- Mid Wales West 132kV: 150 MW waiting
- Gwyddelwern 400kV: 233 MW waiting
- North Wales connection Node A 400kV: 1,273 MW waiting
- Bodelwyddan 400kV: 3,468 MW waiting