Pentir 400kV: grid connection queue
Pentir 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,082 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2028 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fferm Solar Pentir | LIGHTSOURCE SPV 191 LIMITED | Battery storage | 57 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | 2 |
| Pentir Green Energy Centre | INNOVA RENEWABLES LIMITED | Solar + storage | 1,025 | 30 Oct 2037 | Low | 30 Oct 2037 | Awaiting Consents | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 21 Jul 2026 | Fferm Solar Pentir | 1 May 2027 | 31 Oct 2028 | +18 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dolgarrog Gt2 | SP Energy Networks | 5.9 km | 15 MW | 17 MW |
| Dolgarrog T2 | SP Energy Networks | 5.9 km | -1.5 MW | 2.5 MW |
| Dolgarrog T1 | SP Energy Networks | 5.9 km | -1.5 MW | 2.5 MW |
| Dolgarrog T1 | SP Energy Networks | 5.9 km | -1.5 MW | 2.5 MW |
| Dolgarrog Gt2 | SP Energy Networks | 5.9 km | 15 MW | 17 MW |
| Dolgarrog T2 | SP Energy Networks | 5.9 km | -1.5 MW | 2.5 MW |
Thinking of connecting near Pentir 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bodelwyddan 400kV: 3,468 MW waiting
- North Wales connection Node A 400kV: 1,273 MW waiting
- Trawsfynydd 275kV: 940 MW waiting
- Gwyddelwern 400kV: 233 MW waiting
- Wylfa South 400kV: 1,080 MW waiting