Benzene

Wylfa South 400kV: grid connection queue

Wylfa South 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,080 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2029 to 30 Nov 2037.

3projects in the queue
1,080 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Mon Solar FarmLIGHTSOURCE SPV 204 LIMITEDSolar + storage36030 Oct 2029Medium30 Oct 2029Scopingnone
Lightsourcebp Amlwch BESS and HydrogenLightsource Renewable UK Development LimitedBattery storage60030 Oct 2037Low30 Oct 2037Scoping1
Lightsource Mon Solar 2LIGHTSOURCE SPV 204 LIMITEDSolar + storage12030 Nov 2037Low30 Nov 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Mona T1SP Energy Networks4.3 km6.1 MW5.2 MW
Llangefni T1SP Energy Networks6.2 km11 MW3.5 MW
Llangefni Ind Est T2SP Energy Networks6.9 km1.7 MW5.8 MW
Llangefni Ind Est T1SP Energy Networks6.9 km1.7 MW5.8 MW
Llanddeusant T1SP Energy Networks7.3 km3.5 MW
Llanfaelog T1SP Energy Networks9.5 km1.2 MW1.1 MW

Thinking of connecting near Wylfa South 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points