Benzene

Wylfa 132kV: grid connection queue

Wylfa 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 120 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Jun 2029 to 30 Jun 2029.

1project in the queue
120 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Wylfa SubstationWYLFA GREEN LIMITEDSolar + storage12030 Jun 2029Medium30 Jun 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Mona T1SP Energy Networks4.3 km6.1 MW5.2 MW
Llangefni T1SP Energy Networks6.2 km11 MW3.5 MW
Llangefni Ind Est T2SP Energy Networks6.9 km1.7 MW5.8 MW
Llangefni Ind Est T1SP Energy Networks6.9 km1.7 MW5.8 MW
Llanddeusant T1SP Energy Networks7.3 km3.5 MW
Llanfaelog T1SP Energy Networks9.5 km1.2 MW1.1 MW

Thinking of connecting near Wylfa 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points