Penrhos: grid connection queue

Penrhos GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 390 MW are waiting to connect here (largest by capacity: mixed and other, hydro, pumped storage and tidal). Contracted dates run from 30 Oct 2025 to 31 Mar 2028.

2projects in the queue
390 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
180 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Recell at Penrhos (BEGA)Recell Energy Bloom Developments LimitedMixed and other21030 Oct 2025n/aScoping1
Menter Mon Morlais Anglesey Marine EnergyMenter Môn Morlais LimitedHydro, pumped storage and tidal18031 Mar 2028High13 Nov 2030Under Construction/Commissioningnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
7 Jul 2026Recell at Penrhos (BEGA)30 Jun 202631 Oct 2027+16 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Parc Cybi T2SP Energy Networks0.7 km1.9 MW6.5 MW
Parc Cybi T1SP Energy Networks0.7 km1.9 MW6.5 MW
Alpoco T1SP Energy Networks0.9 km4.8 MW
Holyhead T1SP Energy Networks1.5 km4.9 MW
Llaingoch T1SP Energy Networks3.2 km4.2 MW
Caergeiliog Gt1SP Energy Networks5.0 km4 MW-1.9 MW

Thinking of connecting near Penrhos?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report