Mid Wales Connection Node A: grid connection queue

Mid Wales Connection Node A · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 172 MW are waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

2projects in the queue
172 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
GALILEO 08 LIMITEDGALILEO 08 LIMITEDMixed and other10031 Oct 2037Low31 Oct 2037Scopingnone
Calon y GwyntWind 2 Project 3 LimitedMixed and other7231 Oct 2037Low31 Oct 2037Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Mochdre T1SP Energy Networks7.5 km8.3 MW4.1 MW
Milford T1SP Energy Networks7.7 km3.2 MW
Caersws T1SP Energy Networks8.5 km8.1 MW3.8 MW
Llanidloes T1SP Energy Networks9.2 km-3.5 MW1.5 MW
Llanidloes T2SP Energy Networks9.2 km-3.5 MW1.5 MW
Newtown Gt2SP Energy Networks10.4 km16 MW61 MW

Thinking of connecting near Mid Wales Connection Node A?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.