Rassau 400kV: grid connection queue
Rassau 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.
1project in the queue
400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Rassau | ENSO GREEN HOLDINGS Q LIMITED | Mixed and other | 400 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Rassau 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rassau: 165 MW waiting
- Rhigos 400kV: 1,081 MW waiting
- Rhigos B 400kV: 221 MW waiting
- Hirwaun: 120 MW waiting
- Mid Wales Connection Node A: 172 MW waiting